27 July → 21 August 2020

Sidewalk Public Consultation

The Sidewalk Public Consultation will close August 21, 2020. 

24 September 2020

Committee of the Whole

Report to Council regarding the Capital Reconstruction/Construction Project sidewalk locations to be completed in 2020 and the comments provided by the public. 

01 October → 22 October 2020

Capital Reconstruction/Construction 2020 Tender

Put out Tender for sidewalk reconstruction/construction to be completed in October of 2020. Please note these are tentative dates and maybe subject to change.

26 October → 28 November 2020

Award Capital Reconstruction/Construction Tender